Whilst extending my felicitations to the University of Colombo on the centenary celebrations of the Faculty of Arts and the Library of the University, I would like to record my contribution towards these two units as the Registrar of the University.
It was during Prof. Stanley Wijesundera’s tenure as the Vice-Chancellor (VC) in 1980 that the proposals for the buildings in respect of the Chemistry Department, Physics Department, New Administration, Faculty of Law, Faculty of Arts and the Library were mooted and submitted to the Treasury. At that time it was the National Buildings Consortium that assigned the Consultants and the Contractors for the new buildings to be constructed. Within that year the Treasury allocated sufficient funds for the Chemistry, Physics, Faculty of Law and the New Administration buildings. However, no funds were allocated to the Faculty of Arts and only Rs. 7.5 million was allocated for the Library building.
With the funds allocated the Chemistry, Physics, Law Faculty and the new Administration buildings were able to get off the ground. The construction work in respect of the other two buildings could not commence due to non-allocation of sufficient funds, even though the consultants and the contractors and already been selected.
As the Minister of Finance at that time was from Matara, he was more interested in getting the required buildings for the newly established University of Ruhuna completed, which was in his electorate. This meant that the University of Colombo would not get any funds for new buildings other than those buildings where the construction work had already begun.
The university needed a building for the Faculty of Arts very badly as this Faculty had the largest number of students. The Vice-Chancellor requested me to draft a letter to the Minister of Finance. Accordingly, I drafted a letter and submitted to the VC for his signature. He told it was an excellent letter, and he signed without a single amendment and submitted same to the Minister. The Minister approved the releasing of the funds. Now the consultants to the building project studied the area required for the building and found that a small portion of land was necessary from the land of the Planetarium. My efforts to get the land from the person in charge of the Planetarium, the Senior Assistant Secretary and the Secretary himself were not fruitful. I told the VC of the position and that he would have to speak to the Minister in charge of the Planetarium, Mr. Lionel Jayathilaka. He got the Minister on line and addressing him by his first name and informed the Minister of the problem. The Minister immediately got it attended to. However, when the construction work started, they found that the additional land area was not necessary.
At that time, the payments to the consultants of building projects was 15% of the total value of the cost. So, in designing the building they tried to add various unnecessary items to jack up the cost. When the first phase was completed, the building looked monstrous and it was like a maze, as it was difficult to find your way out once you get in. I requested the architect to add some coloured tiles on the floors and the stairway and a few decorations on the walls. The university had a never ending tussle with the contractor as he was like Shylock asking for more, when everything had been paid. He tried various tactics but did not succeed in getting anything more as I was adamant not to give in.
When the second stage of the building project came up, I told the consultant to drop all the unnecessary items and have a straight forward building. This was done by the new contractor at much less cost to the university.
The Library building was the last of the buildings planned in 1980 that was awaiting construction. When Mr. Richard Pathirana became the Minister of Higher Education, I spoke to the two engineers who were assigned the task of supervising the building projects of the universities, and managed to get the funds passed by the Treasury for the construction of the Library building. When the Minister came on a visit to the university, he told me that the building that should have been done for Rs.7.5 million will cost Rs.253 million. I told him that the Treasury never gave any money after approving the initial funding of Rs.7.5 million. Anyway, I had achieved what I wanted to do and the building was successfully completed. Now the furniture for the Library had to be procured. When quotations were called the suucessful tenderer had brought a sample of the study tables. I rejected this as it was inferior to what I wanted and asked the officer concerned to get the design of the furniture from the library in the University of Peradeniya. This was done and the furniture was installed. The official opening of the new Library was arranged. By that time I had retired from the position of Registrar and was the Director of the Institute of Workers’ Education. Even though I was instrumental in getting the building done, I was not invited for the function. That is gratitude!!