Long-term generation expansion plan – Legal barrier against implementing the Electricity Act

Published

on

By Dr. Janaka Ratnasiri and Eng. Parakrama Jayasinghe

A retired Professor of Electrical Engineering has claimed that “the CEB’s long-term generation expansion (LTGE) plan is the best strategy for this country to follow at this time, which is revised once or twice a year” in a write up appearing in The Island of 03.09.2020. Obviously, the learned Professor does not seem to be familiar with the CEB plan because it is not revised once or twice a year but only once in two or three years. Nor has he studied the proposals made by the CEB in relation to the current developments in the energy sector worldwide. The LTGE Plan has some importance for Sri Lanka because compliance with it has been made mandatory for capacity addition both in the Act as well as in the Power Ministry mandate.

SRI LANKA ELECTRICITY (AMENDMENT) ACT NO. 31 OF 2013

This Act, which is an amendment to the Sri Lanka Electricity Act No. 20 of 2009, governs the addition of any new power plants or expansion of existing power plants in Sri Lanka. This amendment to the Act requires that such addition of generation capacity needs to comply with the CEB’s LTGE Plan which has received the prior approval of the Public Utilities Commission of Sri Lanka (PUCSL). There are six instances in the Act where reference has been made to the CEB’s LTGE Plan making it mandatory that any new capacity addition or expansion has to meet the requirements specified in the CEB Plan.

Some extracts of sections of the Act where reference has been made to the LTGE Plan are given below.

“A transmission licensee shall, based on the future demand forecast as specified in the Least Cost Long Term Generation Expansion Plan prepared by such licensee and as amended after considering the submissions of the distribution and generation licensees and approved by the Commission, submit proposals to proceed with the procuring of any new generation plant or for the expansion of the generation capacity of an existing plant, to the Commission for its written approval”.

“Upon obtaining the approval of the Commission under subsection (2), the transmission licensee shall in accordance with the conditions of its transmission licence and in compliance with any rules that may be made by the Commission relating to procurement, call for tenders by notice published in the Gazette, to develop a new generation plant or to expand the generation capacity of an existing generation plant, as the case may be, as shall be specified in the notice”

“Upon the close of the tender, the transmission licensee shall through a properly constituted tender board, recommend to the Commission for its approval, the person who is best capable of meeting the requirements of the Least Cost Long Term Generation Expansion Plan of the transmission licensee duly approved by the Commission”, among others.

“The Commission shall be required on receipt of any recommendations of the transmission licensee, to grant its approval at its earliest convenience, where the Commission is satisfied that the recommended price for the purchase of electrical energy or electricity generating capacity meets the principle of least cost and the requirements of the Least Cost Long Term Generation Expansion Plan and that the terms and conditions of such purchase is within the accepted technical and economical parameters of the transmission licensee”.

“For the purpose of this section- “Least Cost Long Term Generation Expansion Plan” means a plan prepared by the transmission licensee and amended and approved by the Commission on the basis of the submissions made by the licensees and published by the Commission, indicating the future electricity generating capacity requirements determined on the basis of least economic cost and meeting the technical and reliability requirements of the electricity network of Sri Lanka which is duly approved by the Commission and published in the Gazette from time to time”.

 

MINISTRY OF POWER MANDATE

The recently established Ministry of Power has stipulated as a key mandate of the Power Ministry the following:

Meeting the electricity needs of all urban and rural communities based on the long-term generation expansion (LTGE) plan prepared by the Ceylon Electricity Board (CEB).

Among the special priority areas identified for the Power Ministry is the Implementation of the long-term generation expansion plan.

LONG-TERM GENERATION

EXPANSION PLAN

Since the Electricity Act as well as the Ministry of Power mandate require that the generation capacity addition needs to be carried out meeting the requirements of the LTGE Plan, it is necessary to examine closely what this plan is. The CEB prepares a long-term generation expansion (LTGE) plan once in two or three years outlining the least cost options of generation plants that need to be added to the system annually for the next 20 years to meet the forecasted demand. The latest plan is in respect of the period 2020 – 2039 but it is still in the draft form yet to be approved by the PUCSL as required by the Sri Lanka Electricity Act No. 31 of 2013. As such the LTGP in effect is the 2018-2037 plan which has received the written approval of the PUCSL.

Being a rolling plan updated once in two or three years, the types and capacities to be added in a given period keeps changing with the plan. Hence, a potential developer is at a loss to know which plan to follow in planning a future power plant development project. This becomes clear when the capacities recommended to be added in the three recent plans covering the periods 2015-34, 2018-37 and 2020-39 (Draft) given in Table 1 are examined. For simplicity, only the additions of large thermal power plant capacities are included in the Table.

It is seen that the 2015-34 Plan has included only coal power plants amounting to 3,200 MW up to 2034. The 2018-37 Plan, on the other hand, has included addition of 2,700 MW of coal power plants together with 1,500 MW of natural gas (NG) power plants, up to 2036. Whereas the 2020-39 Plan (Draft) has included addition of 2,100 MW of coal power plants together with 3,000 MW of NG power plants up to 2039. When the capital cost of power plants and fuel costs keep varying year to year, it is impossible to forecast accurately 20 years earlier what the cheaper option would be in 20 years hence.

 

ISSUES IN IMPLEMENTING

THE CEB PLAN

If the CEB Plan was implemented in 2016, by 2025, coal power of capacity 1,400 MW, including the proposed coal power plant at Sampur, needs to be built according to 2015-34 Plan. However, according to the 2018-37 Plan, 3×300 MW of coal power plants, together with 2×300 NG power plants, need to be built by 2025. On the other hand, according to the 2020-39 draft Plan, 3×300 MW of coal power plants together with 4×300 MW of NG power plants need to be built by 2025. When a plan keeps changing in this manner with so much divergent recommendations, it cannot be called a long-term plan. There is no unique recommendation for a given period for an investor to pursue. If the 2015-34 Plan decided that coal power plants are the cheap option up to 2025, how is that the 2018-37 Plan decided that NG power plants are the cheaper option for this period? This shows the weakness of the planning methodology.

If an investor wishes to build a power plant in 2015, he is required to follow the capacity additions as specified in the 2015-34 Plan and will decide to build a coal power plant. After spending the first two years on the preliminaries such as feasibility studies and environment impact studies, he finds that an updated 2018-37 Plan released in 2018 recommends NG power plants, instead. Is he then required to change his plans and start building a NG power plant instead? In view of environmental consideration, a NG power plant is always preferred to a coal power plant. It should be noted that a 300 MW coal plant will generate about 100,000 t of ash annually which is an environmental hazard.

There is also an ambiguity in applying the condition laid down in the Act that the capacity additions shall meet the requirements of the LTGE Plan. The Act does not specify whether the Plan to be applied is what is in force at the time of commencing the power plant project or what is in force at the time of commissioning the power plant. Within a matter of four to five years’ time taken to build a coal power plant, the requirements in the Plan could change widely during this period. Hence, it is essential that this be clearly specified or this condition removed altogether enabling implementation of the Act without leaving room for it to be questioned in a court of law.

 

DISPUTE BETWEEN THE REGULATOR AND THE LICENSEE

The Electricity Act requires that the LTGE Plan prepared by the CEB shall be approved by the regulator, PUCSL. However, the approval of the Plan for 2018-37 ran into a problem when the original draft submitted by the CEB was not approved by the PUCSL who in turn proposed an alternative Plan which was not accepted by the CEB. This dispute went dragging for over a year and settled only after the intervention of the President. Even in the case of the current draft for 2020-39, the CEB had submitted it to the PUCSL for approval last year, and is still awaiting approval. Possibly, the PUCSL may want the Plan to fall in line with the Government policy of giving priority for renewable energy sources as described in the writer’s article appearing in the The Island of 25th and 26th September.

This dispute was brought to stark reality in respect of the CEB plan 2018-2037 both by the evaluations of the PUCSL and in the submissions made during the public hearings. The blatant errors and misrepresentation sin the draft submitted by the CEB which was obviously done to force the adoption of further coal power plants ignoring the world wide rejections can be seen in the submissions made to the PUCSL during the public hearings and is available in the PUCSL web page ().

Accordingly, an amended LTGP was formally issued by the PUCSL which should be considered as the LTGP in force until such time a new plan is approved after going through the processes including the public hearings as done in the case of the 2018-2037 LTGP. The fact that the CEB refused to accept this plan and the fact that the Government decided to force the PUCSL to issue an approval for the flawed plan submitted by the CEB makes a mockery of the entire process and the role of the PUCSL as the regulator of the Electricity Sector. As such, it does not make sense to incorporate such a flawed variant plan as mandatory for capacity addition in the Act as well as in the Ministry mandate and to describe it as the best strategy. As a matter of fact, it is the worst strategy for power sector development in the country.

 

AMENDMENT TO THE ELECTRICITY ACT AND MINISTRY MANDATE

To get over the problem of the Act and the Ministry mandate not being able to meet the requirements of the LTGE Plan in view of the uncertainty of the technologies which the Plan recommends for different time periods, it is necessary to amend these two documents. The first reference to the LTGE Plan in the Electricity Act described previously says that procurement of generation capacity shall be based on “the future demand forecast as specified in the Least Cost Long Term Generation Expansion Plan”. This is in order because there is little variation in the demand for a given year between different Plans.

The rest of the references say that future capacity additions shall meet the requirements of the LTGE Plan. Since the requirements include the technology whether a coal plant or a NG plant should be installed and this changes from Plan to Plan causing the uncertainty in implementing the provisions in the Act or the Ministry mandate, it is best if these sections are amended. It is proposed that the words “meet the requirements of the LTGE Plan” appearing in the Act be amended to read “meet the demand forecasted in the LTGE Plan”, wherever the term “requirements” appear.

The Act says that “Upon obtaining the approval of the Commission the transmission licensee shall in accordance with the conditions of its transmission licence and in compliance with any rules that may be made by the Commission relating to procurement, call for tenders by notice published in the Gazette, to develop a new generation plant or to expand the generation capacity of an existing generation plant, as the case may be, as shall be specified in the notice”. Hence, it is logical to keep the fuel option open when calling tenders at the time capacity addition is required giving sufficient time for the procurement process and construction of the plant. The bids received would show which fuel option is the cheaper.

It is important to issue a set of specification with respect to performance and emissions which should be met by the plant offered. The tender should also be required to specify the levelized cost of generation including the amortized annual cost of the plant, cost of operation and maintenance and the fuel cost for generating a unit of electricity giving a formula to work out the fuel cost depending on its price in the international market. The price should also include the cost of externalties. It will be then possible to select the best and cheaper option, whether coal or gas, meeting the specifications.

It should also be noted that the Electricity Act has interpreted “least cost of generation” to mean “least economic cost of generation”. Economic cost should include the cost of damage to the environment due to emission of fly ash as well as from accumulation of about 100,000 tonnes of bottom ash annually from a 300 MW coal plant. It should also include the cost of health damage to people exposed to gaseous emissions and release of toxic substances from the plant. The current plans do not include these and if they are included, all the coal plants included in CEB’s LTGE Plans need to be changed to NG power plants as such plants do not cause emission of toxic gases or other substances.

 

CONCLUSION

Though the Electricity Act and the Ministry mandate stipulate that capacity additions be carried out to meet the requirements of the CEB’s LTGE Plan, practically it is not possible to follow this in view of the fact that the type of plants to be added keep changing with the Plan. It is therefore proposed that the Act as well as the Ministry mandate be amended suitably. It is also proposed that the type of plant be selected after calling tenders keeping the fuel option open a few years ahead when the capacity addition is required and not 20 s years beforehand.

It is important to recognize that the basic purpose of the LTGP is to ensure the long-term energy security of the country using means and technologies that enables realization of the least economic cost of generation, which should include the cost of externalities. As such, unless a firm binding feed in tariff over the life of the plant cannot be guaranteed via suitable tender procedure accepting the above premise, making any long term plans using numbers such as parity rate and price of coal or gas is a futile exercise.

Furthermore, the changes occurring in the energy sector practically every day which helps to realize the above objectives must constantly be factored in to the planning process. Thus, the CEB plans available currently certainly comprise the worst strategy to follow in developing the power sector in the country, as they completely ignore the very progressive advances made the world over which are of great benefit to Sri Lanka.



Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Features

The heart-friendly health minister

Published

on

Dr. Ramesh Pathirana

by Dr Gotabhya Ranasinghe
Senior Consultant Cardiologist
National Hospital Sri Lanka

When we sought a meeting with Hon Dr. Ramesh Pathirana, Minister of Health, he graciously cleared his busy schedule to accommodate us. Renowned for his attentive listening and deep understanding, Minister Pathirana is dedicated to advancing the health sector. His openness and transparency exemplify the qualities of an exemplary politician and minister.

Dr. Palitha Mahipala, the current Health Secretary, demonstrates both commendable enthusiasm and unwavering support. This combination of attributes makes him a highly compatible colleague for the esteemed Minister of Health.

Our discussion centered on a project that has been in the works for the past 30 years, one that no other minister had managed to advance.

Minister Pathirana, however, recognized the project’s significance and its potential to revolutionize care for heart patients.

The project involves the construction of a state-of-the-art facility at the premises of the National Hospital Colombo. The project’s location within the premises of the National Hospital underscores its importance and relevance to the healthcare infrastructure of the nation.

This facility will include a cardiology building and a tertiary care center, equipped with the latest technology to handle and treat all types of heart-related conditions and surgeries.

Securing funding was a major milestone for this initiative. Minister Pathirana successfully obtained approval for a $40 billion loan from the Asian Development Bank. With the funding in place, the foundation stone is scheduled to be laid in September this year, and construction will begin in January 2025.

This project guarantees a consistent and uninterrupted supply of stents and related medications for heart patients. As a result, patients will have timely access to essential medical supplies during their treatment and recovery. By securing these critical resources, the project aims to enhance patient outcomes, minimize treatment delays, and maintain the highest standards of cardiac care.

Upon its fruition, this monumental building will serve as a beacon of hope and healing, symbolizing the unwavering dedication to improving patient outcomes and fostering a healthier society.We anticipate a future marked by significant progress and positive outcomes in Sri Lanka’s cardiovascular treatment landscape within the foreseeable timeframe.

Continue Reading

Features

A LOVING TRIBUTE TO JESUIT FR. ALOYSIUS PIERIS ON HIS 90th BIRTHDAY

Published

on

Fr. Aloysius Pieris, SJ was awarded the prestigious honorary Doctorate of Literature (D.Litt) by the Chancellor of the University of Kelaniya, the Most Venerable Welamitiyawe Dharmakirthi Sri Kusala Dhamma Thera on Nov. 23, 2019.

by Fr. Emmanuel Fernando, OMI

Jesuit Fr. Aloysius Pieris (affectionately called Fr. Aloy) celebrated his 90th birthday on April 9, 2024 and I, as the editor of our Oblate Journal, THE MISSIONARY OBLATE had gone to press by that time. Immediately I decided to publish an article, appreciating the untiring selfless services he continues to offer for inter-Faith dialogue, the renewal of the Catholic Church, his concern for the poor and the suffering Sri Lankan masses and to me, the present writer.

It was in 1988, when I was appointed Director of the Oblate Scholastics at Ampitiya by the then Oblate Provincial Fr. Anselm Silva, that I came to know Fr. Aloy more closely. Knowing well his expertise in matters spiritual, theological, Indological and pastoral, and with the collaborative spirit of my companion-formators, our Oblate Scholastics were sent to Tulana, the Research and Encounter Centre, Kelaniya, of which he is the Founder-Director, for ‘exposure-programmes’ on matters spiritual, biblical, theological and pastoral. Some of these dimensions according to my view and that of my companion-formators, were not available at the National Seminary, Ampitiya.

Ever since that time, our Oblate formators/ accompaniers at the Oblate Scholasticate, Ampitiya , have continued to send our Oblate Scholastics to Tulana Centre for deepening their insights and convictions regarding matters needed to serve the people in today’s context. Fr. Aloy also had tried very enthusiastically with the Oblate team headed by Frs. Oswald Firth and Clement Waidyasekara to begin a Theologate, directed by the Religious Congregations in Sri Lanka, for the contextual formation/ accompaniment of their members. It should very well be a desired goal of the Leaders / Provincials of the Religious Congregations.

Besides being a formator/accompanier at the Oblate Scholasticate, I was entrusted also with the task of editing and publishing our Oblate journal, ‘The Missionary Oblate’. To maintain the quality of the journal I continue to depend on Fr. Aloy for his thought-provoking and stimulating articles on Biblical Spirituality, Biblical Theology and Ecclesiology. I am very grateful to him for his generous assistance. Of late, his writings on renewal of the Church, initiated by Pope St. John XX111 and continued by Pope Francis through the Synodal path, published in our Oblate journal, enable our readers to focus their attention also on the needed renewal in the Catholic Church in Sri Lanka. Fr. Aloy appreciated very much the Synodal path adopted by the Jesuit Pope Francis for the renewal of the Church, rooted very much on prayerful discernment. In my Religious and presbyteral life, Fr.Aloy continues to be my spiritual animator / guide and ongoing formator / acccompanier.

Fr. Aloysius Pieris, BA Hons (Lond), LPh (SHC, India), STL (PFT, Naples), PhD (SLU/VC), ThD (Tilburg), D.Ltt (KU), has been one of the eminent Asian theologians well recognized internationally and one who has lectured and held visiting chairs in many universities both in the West and in the East. Many members of Religious Congregations from Asian countries have benefited from his lectures and guidance in the East Asian Pastoral Institute (EAPI) in Manila, Philippines. He had been a Theologian consulted by the Federation of Asian Bishops’ Conferences for many years. During his professorship at the Gregorian University in Rome, he was called to be a member of a special group of advisers on other religions consulted by Pope Paul VI.

Fr. Aloy is the author of more than 30 books and well over 500 Research Papers. Some of his books and articles have been translated and published in several countries. Among those books, one can find the following: 1) The Genesis of an Asian Theology of Liberation (An Autobiographical Excursus on the Art of Theologising in Asia, 2) An Asian Theology of Liberation, 3) Providential Timeliness of Vatican 11 (a long-overdue halt to a scandalous millennium, 4) Give Vatican 11 a chance, 5) Leadership in the Church, 6) Relishing our faith in working for justice (Themes for study and discussion), 7) A Message meant mainly, not exclusively for Jesuits (Background information necessary for helping Francis renew the Church), 8) Lent in Lanka (Reflections and Resolutions, 9) Love meets wisdom (A Christian Experience of Buddhism, 10) Fire and Water 11) God’s Reign for God’s poor, 12) Our Unhiddden Agenda (How we Jesuits work, pray and form our men). He is also the Editor of two journals, Vagdevi, Journal of Religious Reflection and Dialogue, New Series.

Fr. Aloy has a BA in Pali and Sanskrit from the University of London and a Ph.D in Buddhist Philosophy from the University of Sri Lankan, Vidyodaya Campus. On Nov. 23, 2019, he was awarded the prestigious honorary Doctorate of Literature (D.Litt) by the Chancellor of the University of Kelaniya, the Most Venerable Welamitiyawe Dharmakirthi Sri Kusala Dhamma Thera.

Fr. Aloy continues to be a promoter of Gospel values and virtues. Justice as a constitutive dimension of love and social concern for the downtrodden masses are very much noted in his life and work. He had very much appreciated the commitment of the late Fr. Joseph (Joe) Fernando, the National Director of the Social and Economic Centre (SEDEC) for the poor.

In Sri Lanka, a few religious Congregations – the Good Shepherd Sisters, the Christian Brothers, the Marist Brothers and the Oblates – have invited him to animate their members especially during their Provincial Congresses, Chapters and International Conferences. The mainline Christian Churches also have sought his advice and followed his seminars. I, for one, regret very much, that the Sri Lankan authorities of the Catholic Church –today’s Hierarchy—- have not sought Fr.

Aloy’s expertise for the renewal of the Catholic Church in Sri Lanka and thus have not benefited from the immense store of wisdom and insight that he can offer to our local Church while the Sri Lankan bishops who governed the Catholic church in the immediate aftermath of the Second Vatican Council (Edmund Fernando OMI, Anthony de Saram, Leo Nanayakkara OSB, Frank Marcus Fernando, Paul Perera,) visited him and consulted him on many matters. Among the Tamil Bishops, Bishop Rayappu Joseph was keeping close contact with him and Bishop J. Deogupillai hosted him and his team visiting him after the horrible Black July massacre of Tamils.

Continue Reading

Features

A fairy tale, success or debacle

Published

on

Ministers S. Iswaran and Malik Samarawickrama signing the joint statement to launch FTA negotiations. (Picture courtesy IPS)

Sri Lanka-Singapore Free Trade Agreement

By Gomi Senadhira
senadhiragomi@gmail.com

“You might tell fairy tales, but the progress of a country cannot be achieved through such narratives. A country cannot be developed by making false promises. The country moved backward because of the electoral promises made by political parties throughout time. We have witnessed that the ultimate result of this is the country becoming bankrupt. Unfortunately, many segments of the population have not come to realize this yet.” – President Ranil Wickremesinghe, 2024 Budget speech

Any Sri Lankan would agree with the above words of President Wickremesinghe on the false promises our politicians and officials make and the fairy tales they narrate which bankrupted this country. So, to understand this, let’s look at one such fairy tale with lots of false promises; Ranil Wickremesinghe’s greatest achievement in the area of international trade and investment promotion during the Yahapalana period, Sri Lanka-Singapore Free Trade Agreement (SLSFTA).

It is appropriate and timely to do it now as Finance Minister Wickremesinghe has just presented to parliament a bill on the National Policy on Economic Transformation which includes the establishment of an Office for International Trade and the Sri Lanka Institute of Economics and International Trade.

Was SLSFTA a “Cleverly negotiated Free Trade Agreement” as stated by the (former) Minister of Development Strategies and International Trade Malik Samarawickrama during the Parliamentary Debate on the SLSFTA in July 2018, or a colossal blunder covered up with lies, false promises, and fairy tales? After SLSFTA was signed there were a number of fairy tales published on this agreement by the Ministry of Development Strategies and International, Institute of Policy Studies, and others.

However, for this article, I would like to limit my comments to the speech by Minister Samarawickrama during the Parliamentary Debate, and the two most important areas in the agreement which were covered up with lies, fairy tales, and false promises, namely: revenue loss for Sri Lanka and Investment from Singapore. On the other important area, “Waste products dumping” I do not want to comment here as I have written extensively on the issue.

1. The revenue loss

During the Parliamentary Debate in July 2018, Minister Samarawickrama stated “…. let me reiterate that this FTA with Singapore has been very cleverly negotiated by us…. The liberalisation programme under this FTA has been carefully designed to have the least impact on domestic industry and revenue collection. We have included all revenue sensitive items in the negative list of items which will not be subject to removal of tariff. Therefore, 97.8% revenue from Customs duty is protected. Our tariff liberalisation will take place over a period of 12-15 years! In fact, the revenue earned through tariffs on goods imported from Singapore last year was Rs. 35 billion.

The revenue loss for over the next 15 years due to the FTA is only Rs. 733 million– which when annualised, on average, is just Rs. 51 million. That is just 0.14% per year! So anyone who claims the Singapore FTA causes revenue loss to the Government cannot do basic arithmetic! Mr. Speaker, in conclusion, I call on my fellow members of this House – don’t mislead the public with baseless criticism that is not grounded in facts. Don’t look at petty politics and use these issues for your own political survival.”

I was surprised to read the minister’s speech because an article published in January 2018 in “The Straits Times“, based on information released by the Singaporean Negotiators stated, “…. With the FTA, tariff savings for Singapore exports are estimated to hit $10 million annually“.

As the annual tariff savings (that is the revenue loss for Sri Lanka) calculated by the Singaporean Negotiators, Singaporean $ 10 million (Sri Lankan rupees 1,200 million in 2018) was way above the rupees’ 733 million revenue loss for 15 years estimated by the Sri Lankan negotiators, it was clear to any observer that one of the parties to the agreement had not done the basic arithmetic!

Six years later, according to a report published by “The Morning” newspaper, speaking at the Committee on Public Finance (COPF) on 7th May 2024, Mr Samarawickrama’s chief trade negotiator K.J. Weerasinghehad had admitted “…. that forecasted revenue loss for the Government of Sri Lanka through the Singapore FTA is Rs. 450 million in 2023 and Rs. 1.3 billion in 2024.”

If these numbers are correct, as tariff liberalisation under the SLSFTA has just started, we will pass Rs 2 billion very soon. Then, the question is how Sri Lanka’s trade negotiators made such a colossal blunder. Didn’t they do their basic arithmetic? If they didn’t know how to do basic arithmetic they should have at least done their basic readings. For example, the headline of the article published in The Straits Times in January 2018 was “Singapore, Sri Lanka sign FTA, annual savings of $10m expected”.

Anyway, as Sri Lanka’s chief negotiator reiterated at the COPF meeting that “…. since 99% of the tariffs in Singapore have zero rates of duty, Sri Lanka has agreed on 80% tariff liberalisation over a period of 15 years while expecting Singapore investments to address the imbalance in trade,” let’s turn towards investment.

Investment from Singapore

In July 2018, speaking during the Parliamentary Debate on the FTA this is what Minister Malik Samarawickrama stated on investment from Singapore, “Already, thanks to this FTA, in just the past two-and-a-half months since the agreement came into effect we have received a proposal from Singapore for investment amounting to $ 14.8 billion in an oil refinery for export of petroleum products. In addition, we have proposals for a steel manufacturing plant for exports ($ 1 billion investment), flour milling plant ($ 50 million), sugar refinery ($ 200 million). This adds up to more than $ 16.05 billion in the pipeline on these projects alone.

And all of these projects will create thousands of more jobs for our people. In principle approval has already been granted by the BOI and the investors are awaiting the release of land the environmental approvals to commence the project.

I request the Opposition and those with vested interests to change their narrow-minded thinking and join us to develop our country. We must always look at what is best for the whole community, not just the few who may oppose. We owe it to our people to courageously take decisions that will change their lives for the better.”

According to the media report I quoted earlier, speaking at the Committee on Public Finance (COPF) Chief Negotiator Weerasinghe has admitted that Sri Lanka was not happy with overall Singapore investments that have come in the past few years in return for the trade liberalisation under the Singapore-Sri Lanka Free Trade Agreement. He has added that between 2021 and 2023 the total investment from Singapore had been around $162 million!

What happened to those projects worth $16 billion negotiated, thanks to the SLSFTA, in just the two-and-a-half months after the agreement came into effect and approved by the BOI? I do not know about the steel manufacturing plant for exports ($ 1 billion investment), flour milling plant ($ 50 million) and sugar refinery ($ 200 million).

However, story of the multibillion-dollar investment in the Petroleum Refinery unfolded in a manner that would qualify it as the best fairy tale with false promises presented by our politicians and the officials, prior to 2019 elections.

Though many Sri Lankans got to know, through the media which repeatedly highlighted a plethora of issues surrounding the project and the questionable credentials of the Singaporean investor, the construction work on the Mirrijiwela Oil Refinery along with the cement factory began on the24th of March 2019 with a bang and Minister Ranil Wickremesinghe and his ministers along with the foreign and local dignitaries laid the foundation stones.

That was few months before the 2019 Presidential elections. Inaugurating the construction work Prime Minister Ranil Wickremesinghe said the projects will create thousands of job opportunities in the area and surrounding districts.

The oil refinery, which was to be built over 200 acres of land, with the capacity to refine 200,000 barrels of crude oil per day, was to generate US$7 billion of exports and create 1,500 direct and 3,000 indirect jobs. The construction of the refinery was to be completed in 44 months. Four years later, in August 2023 the Cabinet of Ministers approved the proposal presented by President Ranil Wickremesinghe to cancel the agreement with the investors of the refinery as the project has not been implemented! Can they explain to the country how much money was wasted to produce that fairy tale?

It is obvious that the President, ministers, and officials had made huge blunders and had deliberately misled the public and the parliament on the revenue loss and potential investment from SLSFTA with fairy tales and false promises.

As the president himself said, a country cannot be developed by making false promises or with fairy tales and these false promises and fairy tales had bankrupted the country. “Unfortunately, many segments of the population have not come to realize this yet”.

(The writer, a specialist and an activist on trade and development issues . )